Firstco uses Value Assured Engineering to save £millions
Thanks to the application of 'Value Assured Engineering' (VAE) by
Firstco, technical consultancy, project management and systems
integration specialists, the Heathrow Express station at Heathrow's new
Terminal 5 has seen an initial systems budget of £25m reduced to an
anticipated final cost of £19m - thus saving some 25 per cent on the
overall cost of the project.
According to Firstco's managing director, Bill Martin: "This
application of VAE, combined with Firstco's use of superior products
and the latest technology, has ensured the success of the project at
every level."
Martin added that VAE offers clients an alternative method of systems
procurement and delivery. By separating the three primary elements of a
typical large systems project and applying individual expertise to each
of them, a more commercially focused solution can be obtained.
Mark Calnan, Firstco's chairman, explained: "Traditionally, because of
their perceived difficulty, systems projects are often awarded to a
single major manufacturer. This appears to give the client a 'one stop
shop' solution, with the selected manufacturer offering all the
required elements 'in house' and so ensuring continuity of design
throughout the various sub-systems.
"However, history shows this is not always the case.
"When large companies are given complete control of systems projects,
they tend to use their own products and solutions. These may not be the
most suitable solutions for the individual project and can lack
innovation," Calnan added.
"There is little or no incentive to drive down costs and members of the
design team feel less responsibility for the project. All these factors
can mean that the client does not get the best available technical
solution at the most economic price.
"On the other hand, we believe that the VAE approach gives the optimum
structure for managing the overall supply of a successful systems
project," he said. "And this has been justified in the case of the
Heathrow Express station at Heathrow_s new Terminal 5."
"VAE has a number of advantages - including tangible cost savings and a
fully assured design," said Martin.
"The equipment selected is the best available and not limited to one
manufacturer or one technology. A concerted effort to achieve and
exceed the project's requirements is guaranteed and the project will be
delivered on time and within budget.
"VAE means 'best in class' systems engineered at the lowest cost by
specialist multidisciplinary teams," he continued. "It ensures the
optimal mix of technologies instead of slavish adherence to boilerplate
products from one manufacturer.
"As our experience has shown, there is unconstrained innovation and a
real commitment to achieving and exceeding the client's requirements."
end
Notes for Editors:
About Value Assured Engineering (VAE)
The three primary elements of VAE are:
· Engineering Design,
· Assurance / Compliance, and
· Cost Management.
By forming a team, drawing expertise from each of these disciplines,
the client is able to realise huge potential savings in overall
delivery costs. The team is headed by a Project Manager - who could be
a member of the client team - assisted by planners and other support
staff depending on the project's size.
All three teams are specialists in their respective disciplines, have a
definite structure and lines of communication - and are responsible for
value, assurance and engineering. The teams have the ability to be
expanded to suit the size of the project.
The Cost Management team has expertise with specific systems knowledge.
It provides detailed equipment and labour budgets, cost control and
earned value reporting throughout the project life cycle, together with
the procurement of specialist packages.
The Assurance team deals with the capture of design, standards, safety,
CDM, EMC, RAMs and human factors - along with traceability, change
control and document control.
Firstco provides the Engineering team, with responsibility for
conceptual and detailed design, asset management, procurement
specifications, sub-contract management, commissioning, operator and
maintenance manuals, operator and maintainer training and optional
maintenance.
For further details on the VAE model, contact Firstco: 0207 034 0833;
www.firstco.uk.com
About Firstco
Established in 1998, Firstco is now a major force in the areas of
technical consultancy, project management and systems integration.
Working in a range of industries - notably transport, especially rail
installations and airports; power and construction - Firstco
specialises in controls and communication solutions for assignments of
all sizes from buildings through to large scale infrastructure
projects.
Firstco's in-house team includes specialists in: electrical
engineering, mechanical engineering, software engineering, consulting,
project management and commissioning management.
Through its core services of consultancy, system delivery and project
management, Firstco provides its clients with a total solution - from
concept to commissioning and maintenance, based on collaboration and
integration with clients and partners.
Its mission is to advise, deliver and support high quality control and
communications solutions that improve transport and workplace
environments, create value for clients and make a positive difference
to their end users.
Firstco's approach is based on four core values:
-
Service Excellence - achieving client confidence by truly understanding
the business drivers and the project requirements, delivering the
agreed solution to plan, managing issues and communicating clearly and
regularly - while being easy to do business with and enjoyable to work
with.
-
Integrity - applying professional and technical expertise to ensure the
right solution for the right reasons, as well as being open, honest and
fair in all of its dealings.
-
Teamwork - deploying the right blend of talent and experience to get
the job done, and integrating effectively with client and third party
personnel and activities.
-
Development - continually seeking to enhance its own capabilities and
processes, enabling it to remain innovative and challenging - and
sharing this with its clients.
Firstco's clients include: BAA Heathrow Airport Ltd; Esso Petroleum;
Heathrow Express Operating Company; London Underground Ltd; Standard
Life Assurance; Morgan Stanley; Arup Associates; Balfour Kilpatrick;
Landis & Gyr; London Electricity Services, and Transmanche Link.