Firstco delivers UK's largest Allen-Bradley SIL2 ControLogix Project
Firstco, one of the UK's leading technical consultancy, project
management and systems integration specialists, has just completed the
Customer Factory Acceptance testing of a ControLogix PLC system that is
believed to be one of the largest of its kind in Europe. The PLC
network architecture was specified by Firstco's design team working, in
partnership with BAA, on the prestigious Terminal 5 (T5) Project at
London's Heathrow Airport.
Five Levels below the Terminal Building is a six platform railway
station that will handle the Heathrow Express and Piccadilly Line
services, as well as providing potential future connection to the South
West lines.
The PLC network controls and monitors all of the T5 Rail Station
systems. These include train information displays, tunnel ventilation,
public address, CCTV, fire and utilities.
The PLC network runs through the 2.5km long Heathrow Express tunnel
linking the T5 site to the existing PLC network at the Heathrow Central
rail station. The entire network will now cover a geographical area of
some 25km as the existing network is linked to both Terminal 4 and
Paddington Station.
Due to the critical nature of the tunnel ventilation system, the PLC
network was specified as having to meet the requirements of BS EN61508
Safety Integrity Level 2. The design was, therefore, based around
Rockwell Automation's Allen-Bradley's ControLogix SIL2 rated range of
equipment.
The new PLC network uses over 10km of redundant cabling, both copper
and fibre, to connect 23 PLCs on a ControlNet network. Eighteen of the
PLCs are configured as hot standby fully redundant pairs and are SIL2
compliant.
The PLCs are networked to 49 purpose built remote I/O control panels,
giving connection to approximately 2,400 digital and analogue I/O
points. In addition to the hardwired inputs, the system also has seven
separate protocol interfaces allowing the control room staff seamless
control of the various third party systems.
A redundant server/client RSView SCADA System brings all of the systems
together to provide a fully integrated user interface.
An additional single headed workstation will be added to the five
existing triple headed and two single headed workstations currently in
use. The additional control and monitoring required for the new T5
systems has been engineered into the existing graphical user interfaces
(GUIs) to ensure that the entire network, now comprising of 53 PLCs,
appears and operates as one single, integrated system to the operators.
Firstco's managing director, Bill Martin, said: "Ultimately the success
or otherwise of a project such as this is how easy the end users find
the system to operate. By working closely with Heathrow Express we have
been able to deliver a SCADA system that provides the Control Room
operators with a fully integrated user interface that belies the
complexity of the systems at field level.
"Working on a project of this size with some of Rockwell Automation's
latest products and technologies has put us at the forefront of this
type of PLC architecture."
end
Notes for Editors
About Firstco
Established in 1998, Firstco is now a major force in the areas of
technical consultancy, project management and systems integration.
Working in a range of industries - notably transport, especially rail
installations and airports; power and construction - Firstco
specialises in controls and communication solutions for assignments of
all sizes from buildings through to large scale infrastructure
projects.
Firstco's in-house team includes specialists in: electrical
engineering, mechanical engineering, software engineering, consulting,
project management and commissioning management.
Through its core services of consultancy, system delivery and project
management, Firstco provides its clients with a total solution - from
concept to commissioning and maintenance, based on collaboration and
integration with clients and partners.
Its mission is to advise, deliver and support high quality control and
communications solutions that improve transport and workplace
environments, create value for clients and make a positive difference
to their end users.
Firstco's approach is based on four core values:
-
Service Excellence - achieving client confidence by truly understanding
the business drivers and the project requirements, delivering the
agreed solution to plan, managing issues and communicating clearly and
regularly - while being easy to do business with and enjoyable to work
with.
-
Integrity - applying professional and technical expertise to ensure the
right solution for the right reasons, as well as being open, honest and
fair in all of its dealings.
-
Teamwork - deploying the right blend of talent and experience to get
the job done, and integrating effectively with client and third party
personnel and activities.
-
Development - continually seeking to enhance its own capabilities and
processes, enabling it to remain innovative and challenging - and
sharing this with its clients.
Firstco's clients include: BAA Heathrow Airport Ltd; Esso Petroleum;
Heathrow Express Operating Company; London Underground Ltd; Standard
Life Assurance; Morgan Stanley; Arup Associates; Balfour Kilpatrick;
Landis & Gyr; London Electricity Services, and Transmanche Link.
Further information from:
David Blight / Rupert Exham, Firstco, 0207 034 0833;
www.firstco.uk.com
Bob Little, Bob Little Press & PR, 01727 860405
|